Mainstream Deammonification with Biological Phosphorus Removal

Project Update

Reporting Period: October 2020 – March 2021. During this project period, a 360 L mainstream nitrogen pilot, located at DC Water Blue Plains Advanced Wastewater Treatment Plant, was built and fully operational with the capability to induce different treatment zones.